Jordan Blake

Case study · 2019–now

Trusted identity at enterprise scale

Authentication and identity programmes for banks, government, aerospace, automotive, healthcare and insurance. 40 countries · 6 continents. No client names. That is the job.

Programme Manager, 2019–now · Statements of work, authentication programmes, FDA 21 CFR Part 11

By the numbers

Likelihood to recommend
9.1/10
Of surveyed clients satisfied
94%
Booked work since 2019
$5m+
Statements of work and clients
180+ · 90+

Problem

These programmes do not fail in the demo. They fail in the gaps between statements of work, regions, and the person who thinks their login is a special case.

A bank programme can have twenty-plus statements of work in flight. A hospital has a regulator. A department has a score at the end. Someone has to keep the work coherent without turning it into theatre.

What I did

I ran a multi-year bank programme of 20+ statements of work, and a two-phase authentication redesign. I delivered a UK government upgrade that came back at 10/10.

Healthcare work was mapped against FDA 21 CFR Part 11, which is a long way of saying the audit trail had to be real. Coverage runs through EMEA, the Americas and APAC, across 40 countries and 6 continents.

Delivery, when the plan meets reality

At HID Global I run identity and access management programmes from the first SOW to go-live and Support handover, across EMEA, the Americas and APAC.

Most of the job is what happens between those two points: holding scope, running change control when the ground moves, and keeping customers, consultants and engineers working to the same plan.

01 Plan baselined. Six months agreed in the SOW, with design, build and enablement running side by side.

Programme management
Solution design
Test environment build
Production deployment
Enablement & integration
UAT
Go-live
Hypercare & handover
Extension · CR-01
Illustrative identity deployment: six-month baseline, customer scope change and three-month extensionEight overlapping workstreams planned over six months. At the start of month 4, during testing, the customer adds technical scope. Scoping takes six weeks and sign-off of the updated design takes six more, pushing production deployment and later phases three months right. Change request CR-01 adds the scope and books a three-month extension. Go-live moves from mid-month 6 to mid-month 9 and the project ends at the end of month 9 instead of month 6.AT RISK · PAST AGREED ENDEXTENSION · 3 MONTHSORIGINAL ENDCustomer adds technical scope in test · 6 wks+ 6 wks knock-on: updated design awaits customer sign-offCR-01 · EXTENSION BOOKEDwas M6Go-live · M9M1M2M3M4M5M6M7M8M9
  • Baseline
  • Planned
  • Complete
  • Customer delay
  • Knock-on
  • Extension
Original endM6
Revised endM6
ExtensionNone
Text version of this chart
  1. Plan baselined. A six-month plan agreed in the SOW. Programme management runs for the whole project. Solution design runs from the start to mid-M3. The test environment build runs from M2 to mid-M4 and overlaps production deployment, planned for M4 to M5. Customer enablement and integration support runs from mid-M1 to mid-M6. UAT is planned for mid-M5 to mid-M6, go-live for mid-M6, and hypercare and Support handover for the second half of M6.
  2. Delivering. Solution design is signed off in M3 and the test environment build is under way, with enablement running alongside.
  3. Customer delay. At the start of M4, during testing, the customer adds technical scope. Scoping it takes six weeks, and the updated design then waits six more weeks for customer sign-off. Production deployment, UAT, go-live and hypercare move three months right. Enablement keeps running, so its end moves to mid-M9.
  4. Extension agreed. Change request CR-01 adds the new scope and books a three-month extension, M7 to M9, before the slip becomes an overrun.
  5. Delivered. The test environment is finished in the first half of M7 and production deployment runs M7 to M8. UAT runs mid-M8 to mid-M9 and go-live lands in mid-M9, then hypercare and Support handover finish by the end of M9. Original end: M6. Revised end: M9. Extension: three months, CR-01.

Illustrative project with dummy data. Not a real customer.

Result

Surveyed clients put likelihood to recommend at 9.1 out of 10. Ninety-four percent said they were satisfied.

The names stay off this page. So do the values.

Anonymised programme board

Data anonymised

Showing 12 of 12. Data anonymised.

  • P-104BankingEMEA20+ SOWs, multi-yearIn flight
  • P-118BankingEMEATwo-phase authentication redesignClosed
  • P-207GovernmentEMEAPlatform upgrade10/10
  • P-221GovernmentAPACDirectory migrationIn flight
  • P-331HealthcareAmericasMapped to FDA 21 CFR Part 11In flight
  • P-340HealthcareEMEAIdentity controlsClosed
  • P-412AerospaceAmericasWorkforce authenticationIn flight
  • P-428AerospaceEMEAPrivileged access reviewClosed
  • P-505AutomotiveAPACPlant identity rolloutIn flight
  • P-519AutomotiveEMEASupplier accessClosed
  • P-602InsuranceEMEACustomer authenticationIn flight
  • P-617InsuranceAmericasAgent desktop loginClosed

Data anonymised. Codes are not clients.